Voters approved a $117 million bond referendum on February 6, 2018, to build a second high school and make improvements to the current high school facility. The bond referendum passed with a 90.27 percent voter approval. Sixty percent approval was needed.
Sports fields and improvement costs will be paid for using funds from the Physical Plant and Equipment Levy (PPEL).
Total Project Cost $135,878,088
Site Development: $12,679,730
- Grading, Control, Stabilization: $5,188,730
- Paving, Utilities, Landscaping, Improvements: $7,491,000
Building Construction Subtotal: $100,854,730
Sports Fields & Improvements: $19,391,574
Sports fields and improvement costs will be paid for using funds from the Physical Plant and Equipment Levy (PPEL).
- Football Stadium, Team Building, Amenities: $11,000,000
- Tennis Courts & Practice Fields: $1,848,000
- Baseball & Softball Fields, Concession/Storage: $2,750,000
- Professional Fees (Sports Fields): $1,013,674
- 5% Design/Const. Contingency: $779,900
- YMCA Pool Project: $2,000,000
Project Development Soft Costs: $12,031,784
- Topographical Survey: City Cost
- Soil Investigation: $36,700
- Soil Investigation Staking: $5,000
- Printing of Documents: $75,000
- Construction of Special Testing: $285,000
- Sanitary Sewer Fee: $445,000
- Building Permit Fee: $176,000
- Water/Sewer Connection Fees: $60,000
- Life Cycle Cost Analysis: $25,000
- Builder’s Risk Insurance: $75,000
- Energy Code Inspections: $400,000
- Professional Fees: $5,757,848
- 5% Design/Construction Contingency: $4,592,737